Saturday, February 26, 2000
Stadium manager: Deadline can be met
BY DAN KLEPAL
The Cincinnati Enquirer
![[stadium]](http://bengals.enquirer.com/img/photos/2000/02/022600stadium180.jpg)
Stadium construction is two months behind schedule. (Steven M. Herppich photo) | ZOOM | |
The beer taps are in and the bathrooms are nearly done, but the amount of work left to do on Paul Brown Stadium is staggering. Still, Project Manager Dan Streyle says it will all get done during the next six months and that the Bengals stadium will be open for business on Aug. 19.
Valuable time has recently been lost because the Ohio River crested above flood stage. That time will be made up with more people working more hours.
How much all that will add to the bottom line of a 66,000-seat stadium, already estimated to cost $45 million more than expected, is unknown.
We've got a lot of work to do, I won't kid you, Mr. Streyle said. But I'm still feeling pretty confident that we'll make the deadline. Each preseason game played at Cinergy Field means a $2 million penalty paid to the Bengals.
Mr. Streyle said it's impossible for him to estimate how many more days lost would cause the project to miss the deadline.
We're at the stage that we never lose a full day of work because we'll always be able to work in some places, he said. I can't answer that.
Mr. Streyle and the county's public relations people took the media on a tour of the facility Friday.
He would not address cost overruns that an audit blamed on lax oversight over hundreds of changes.
County commissioners last week approved an additional $14 million to keep work moving.
The auditor laid most of the blame for the cost overruns with the stadium project team, consisting of construction manager Turner Barton Malow D.A.G., project man ager Getz Ventures and architect NBBJ.
County records show the project team has been paid more than $40 million of taxpayer money to date $20.7 million to NBBJ, $17.4 million to Turner and $3.3 million to Getz.
We have not had a chance to meet with the auditor, said Mr. Streyle, who is a Getz employee. He said that meeting likely will happen next week.
There are about 800 em ployees working on the stadium on a typical day.
It all very much has to be choreographed, said Mr. Streyle, who estimates the stadium to be 70 percent complete.
The thousands of individual tasks happening at the stadium include:
Assembling the large scoreboard in the south end zone.
Seat mounts are being riveted into the concrete.
The building's facade is being put on.
Crews are preparing to pour concrete in the plaza level.
Mr. Streyle said there will be a lot of work to do after the stadium opens, but that everything needed to safely host a football game will be in the stadium for the first game.
Things not completed by the deadline could include landscaping and painting; some individual light fixtures and signs could need hanging.
Bengals Stories
Boone settled at third
Time for pitchers to get serious
Astros still have look of a contender
Bearcats still playing for top NCAA seed
Price focused on game, not pain
Boxer makes Olympic team
American Cup first big test for White
Miami hits road with 4-game skid
UK looks to rebound against Arkansas
Area swimmers win 5 state swimmers
St. X swimmers poised for title
Ursuline swimmers take big lead
Sectional Wrestling - Division II
Sectional Wrestling - Division I
Sectional Wrestling - Division III
Cincinnati boys basketball scores
Cincinnati boys basketball roundup
Second half lifts Mercy
Cincinnati girls basketball roundup
Ohio boys basketball scores
Ohio girls basketball scores
Kentucky boys basketball scores
Kentucky girls basketball scores
N.Ky. boys basketball roundup
No. 2 Holmes pressed to extend streak
Cyclones 4, Cleveland 1
Kentucky 1, Mighty Ducks 0
Stuff 118, Las Vegas 104